Drivers between Gillette and Wright will see about 10.5 miles of Wyoming Highway 58 resurfaced, the biggest of 10 highway contracts the Wyoming Transportation Commission awarded at its November meeting.

Together, the 10 contracts are worth about $43.9 million, the Wyoming Department of Transportation said in its announcement of the awards.

Montana-based Riverside Contracting Inc. won the Campbell County job with a bid of about $10.7 million. It's a mill, level and overlay project, a resurfacing job, and it has to be done by Oct. 31, 2027.

Besides Campbell, the work reaches Albany, Goshen, Park, Big Horn, Johnson and Natrona counties, plus two intersections in Buffalo.

Most of the money is federal. Nearly every WYDOT project goes to whoever bids lowest, the department said.

Albany County's job is on Interstate 80 between Laramie and Rawlins, where Worland-based McGarvin-Moberly Construction Co. bid about $9.1 million to mill and overlay about 10.5 miles and finish them with a plant mix wearing course.

Goshen County has two contracts worth about $9.1 million combined. Between Yoder Junction E and Huntley, Cheyenne-based Simon Contractors will do full depth reclamation, overlay and chip seal work for about $7.4 million, and it has until June 30, 2028. South of Huntley, Minnesota-based Bituminous Paving Inc. will overlay and scrub seal Wyoming Highway 158 on Table Mountain Road for about $1.7 million, with a Sept. 30, 2027, deadline.

In Park County, Lovell-based Mountain Construction Company won about $5.3 million to mill, overlay and chip seal about 8.6 miles of Wyoming Highway 296, the Chief Joseph Highway. Fencing along that same road went to Cowley-based LandWorks LLC for about $680,000.

Two bridge contracts in Big Horn County total about $5.6 million. Colorado-based Hudick Excavating Inc., which does business as HEI Civil, bid about $4.2 million to replace a bridge and work on a railroad crossing approach on County Road 296 and County Lane 55. TCA Group Inc., based in Montana, will replace the County Road 83 bridge over Shell Creek for about $1.4 million by Oct. 31, 2027.

Culverts get new linings along about 53 miles of Interstate 25 between Casper and Buffalo, in the Kaycee area of Johnson and Natrona counties. Cowley-based Wilson Bros. Construction Inc. won that work for about $2.3 million.

In Buffalo itself, Sheridan-based Advanced Electrical Contracting Inc. bid about $1 million for concrete and electrical work at Main and Fort, and at Fort and Burritt.

HEI Civil's Big Horn County bridge job runs latest of all, with an Oct. 31, 2028, deadline.